By Kebba AF Touray
The Gambia Ports Authority has failed to achieve efficient vessel turnaround times, suffers from chronic congestion, and lacks the legal framework to attract private investment, according to a follow-up performance audit published in September 2025 by the National Audit Office.
The findings, contained in the NAO’s audit report on cargo handling at the GPA, paint a troubling picture of an institution struggling to keep pace with growing trade demands at the Port of Banjul — the country’s primary gateway for imports and exports.
At the heart of the audit’s concerns is the GPA’s inability to turn vessels around quickly. The NAO found that the authority “has failed to achieve a short vessel turnaround time due to the limited berth availability, which is unable to optimally handle vessel calls, lack of modern port equipment to fast-track vessel unloading and loading, inefficient stevedores, and congested terminal space.”
The convergence of these factors, auditors noted, creates a compounding bottleneck that delays cargo movement and raises costs for importers and exporters operating through Banjul.
The NAO recommended that GPA management consider upgrading and increasing berth capacity to match the demands of modern vessels and to respond to current port conditions.
The Port of Banjul does not have adequate terminal space to handle its current cargo volume, the audit found. The shortage of space has forced port operators to resort to substandard stacking methods for container cargo — a workaround that restricts the movement of equipment, increases the number of container shifts required, and accelerates wear on port machinery.
“There is an urgent need for the expansion of the terminals to match the current rate of increased throughput and be able to handle the anticipated increase in the future,” the NAO stated in its recommendations.
The audit also noted that a limited number of operational plants further compounds delays and contributes significantly to slower service delivery across the port.
The NAO raised concerns about the stevedoring workforce at the Port of Banjul. According to the audit, 80 per cent of stevedores are aged 40 years and above, with 18 per cent having already reached the mandatory retirement age of 60 — yet still remaining in the workforce.
The audit warned that GPA management must also urgently address the practice of registered dockworkers subcontracting their duties to untrained individuals, a practice the NAO said “can lead to an occupational hazard and can very likely affect the quality of work rendered by the subcontractors who are not trained and not employees of ports.”
Beyond the physical and workforce challenges, the NAO found that monitoring and oversight mechanisms at the GPA are inadequate. The systems currently in place, auditors said, are not robust enough to set performance indicators or to measure whether the port is operating prudently, efficiently, and effectively.
The audit called on the GPA’s line ministry and other relevant authorities to ensure adequate monitoring mechanisms are put in place to improve performance and service delivery.
Perhaps most consequentially for the port’s long-term development, the NAO found that the Government of The Gambia has failed to develop the legal framework and expertise necessary to facilitate private sector participation in port operations — despite expressed interest from the private sector.
“The mechanisms needed for private sector participation in the port operation are not in place,” the audit stated.
The NAO urged the PPP Unit of the Ministry of Finance and Economic Affairs to complete the drafting of a public-private partnership policy framework “with urgency” and to ensure that all required steps are taken promptly to put it into motion. The framework, auditors said, must be comprehensive enough to address and mitigate the risks inherent in such partnerships.
The Gambia Ports Authority has provided formal responses to the audit findings, though those responses were not included in the initial publication. The GPA’s detailed replies to each of the issues raised are expected to be published in a forthcoming edition.