By Madiba Singhateh
Residents living on the banks of Kotu Stream, which flows from Nema Kunku to Kotu at the shore of the Atlantic Ocean, have faced enormous problems, including floods, health, environmental and other problems. The West Africa Coastal Areas Resilience Investment Project 2 (WACA ResIP 2), a major climate resilience programme funded by the World Bank and implemented in The Gambia to reduce coastal erosion, flooding and environmental degradation. The second phase of the project, known as WACA ResIP 2, was launched in 2023 with a budget of $45 million to be executed over five years is designed to reprofile the stream – enlarge the waterway, build crossing points across different sections of the stream, including bridges, culverts and footbridges.
Since the project should take five years and residents have been expressing concerns as the rainy season approached, a reporter was assigned to find out what their concerns are and what measures WACA plans to take in the interim to alleviate their suffering from floods, solid waste, sewage and loss of livelihood. Their concerns were published, and the WACA management has responded to their claims and concerns as indicated below by taking each claim or concern and explaining or clarifying the underlying policy and plan.
1. Management referred to the following statement in the story: ““With the rainy season approaching, uncertainty is growing among hundreds of residents living along the Kotu Stream, from London Corner to Bundung Borehole.”
In response, management explained the status of planned civil works on the Kotu Stream as follows: “The Feasibility study and engineering designs for the Kotu Stream works were developed by an international consulting firm and their Gambian partners (HydroNova and Luxicon) from February 2025 to May 2026.
The detailed engineering designs were validated on May 13th 2026, by stakeholders, including government technical agencies, CSOs, municipal councils, Ward Councillors, Alkalos, youth, women and persons with disabilities, representatives from all the 9 wards along the Kotu Stream.
The designs were developed with strong stakeholders and community input.
Tender documents have been prepared, awaiting the finalisation of the ESIA.
The ESIA is scheduled to be validated on June 30th 2026.
The procurement process for contractors will begin immediately afterwards.”
2. Residents referred to road construction in an interview, but management made it clear that the project does not include road construction:
“WACA does not construct roads. It’s never been part of the plan.
WACA intends to reprofile the stream – enlarge the waterway, build crossing points across different sections of the stream, including bridges, culverts and footbridges.”
3. One of the residents whose compound has three compounds between it and the canal claims that his compound is marked as part of the project, but management denied this, asserting the following:
“In all the designs – from Nema Kunku to Kotu, nowhere does the buffer extend up to 100 meters from the Stream.
The set back distance on either side of the stream is not uniform and is set based on evidence of flood risk and is necessary to protect communities close to the stream from flooding.”
4. Residents also claim that the rainy season was fast approaching and when the rain comes, flooding is imminent, but they still haven’t seen WACA. Management responded as follows:
“WACA is actively in coordination with communities, and our teams are in the communities regularly.
– The last time our team was at the Stream was on June 10.
– Before that, on May 19, the Honorable Minister of Environment, together with her senior team and the WACA Project, toured the Kotu Stream and held several community meetings to discuss the project and gather community feedback.
– This outreach was followed by a radio program with Honorable Minister on WACA, geared towards updating the public on WACA’s progress and the works ahead
– Regarding the RAP Study, a stakeholder consultation was held with local leaders (Alkalos, Councilors) and community representatives.
– Affected families were also directly contacted and briefed during the studies.
We also have WhatsApp forums for all community members, Alkalos and Councilors to ease communication and register feedback. Our toll-free grievance line (1144) is also active 24/7.”
5. Will there be any relocation under the project and is it necessary? One of the residents felt that they have been living in the area for decades and should not be relocated. Management’s response to this is as follows:
“Per the Kotu Stream designs, some properties need to be removed to make way for the flood mitigation works. This will involve resettlement.
Following the development of the designs, we hired an international firm and their Gambian partners (SAL Ghana and SAL Gambia) to conduct an independent Resettlement Action Plan (RAP) studies. These studies will identify the number and value of the affected properties and form of compensation.
This process ensures that all affected families/households are treated fairly and independently as the consultant engaged with all Project Affected Persons (PAPs) during the RAP studies.
The details of the affected people have been taken, and report will be produced for Government’s action.
As a matter of obligation, all affected families must be compensated before they are relocated or even before work starts.
Decisions about the extent of the affected properties are purely based on scientific evidence.
While some may disagree, the design consultants used advanced tools and techniques to reach the decisions they made about the width and distance of the stream.
The stream is designed to mitigate the risk of flooding not only now but for decades to come.”
6. The issue of compensation arose during the interviews Foroyaa had with the residents. Will affected persons/families be compensated? And what form of compensation will WACA provide for relocated families?
According to management, decisions about what form of compensation to be made will be made with the best interest of the affected persons/families in mind as compensation will consider replacement cost.
7. Many women gardeners in project area will be affected by the project and are concerned about their fate. One of them who needed clarification said, “They took our names and told us they would call us back, but up to now we have not been called,” she said.”
8. As to why hasn’t WACA provided feedback to the livelihoods applicants, management responded as follows:
“The process is still ongoing – it is led by the International Trade Center (ITC), who are our Lead Service Provider.
Following the applications process, applicants were longlisted, interviewed, and then shortlisted. The shortlisted applicants underwent geographical verification process to ensure that applicants live within the designated intervention zone (Kotu Stream).
The final list will be reviewed and approved by a multi-stakeholder Evaluation Committee composed of technical institutions, during their sittings on June 24 2026. The outcome will be communicated to all applicants once decision is made.
It is important to note that this application cycle is just the first phase – subsequent rounds will be communicated.”
9. Waste/littering in the stream which management described as their biggest nightmare is a major issue. Management says though the project has taken numerous approaches to address the issue, it persists. According to them, the following measures have been taken:
– Clearing – every year, as part of our short-term interventions, we clear all the waste across the Kotu Stream, including across 50 meters on either side of the Stream and deposit it at the Bakoteh Dumpsite
– Awareness creation – we have run multiple campaigns on TV, radio, social media and house-to-house sensitizations for the past two years trying to address the waste issue
– Enforcement – we support the National Environment Agency (NEA) to conduct regular joint environmental monitoring and enforcement of the Anti-Littering Regulations 2007 across the Kotu Stream and surrounding communities.
– The Project also supports NEA to conduct radio sensitization programs on the Anti-Littering Regulations 2007, and sound environmental stewardship.
– In addition, the Project is supporting NEA’s Schools Environment Outreach Program (SEOP) by targeting twenty-four (24) schools along the stream to raise awareness on the importance of sound environmental stewardship, green and clean school environment and thereby ensuring positive attitude and behavioral change.
– The Project also provided cleansing materials (120 wheelbarrows, 120 waste bins, and 120 rakes) to NEA for distribution to schools along the Kotu Stream.
10. Residents are concerned about the accumulation of silt in the stream. A resident expressed fear of flooding if no excavation is done. In response management acknowledged that the sand humps accumulated in the stream are part of the sedimentation that affects many parts of the stream, especially upstream and promised that “during the short-term interventions, which are scheduled to start by June 25th, all sand deposits will be cleared, alongside the waste and vegetation that obstructs the flow of water.”
11. Under the project homes and gardens will be lost and the concerned home owners and gardeners are eager to know whether they will receive compensation or relocation. The response of management is as follows:
“In response, management outlined the following as the next steps for the WACA project:
“Finalization of the Environmental and Social Impact Assessment (ESIA) – the ESIA study will be validated on June 30th 2026
Launch of tender for the works – Tenders will be launched immediately after the validation and finalization of the ESIA report. It’s a requirement that the Environmental and Social Management Plan (ESMP) of the ESIA report is attached to the tender documents.
Finalize the RAP – Review the RAP and finalize before the mid of July 2026
Initiate implementation – work with the government to begin the implementation of the RAP. People who need to be resettled or whose livelihoods will be affected will be fairly compensated.”
Management says works are expected to start before the end of 2026.
Discussion