By Kebba A.F. Touray

The Minister for Petroleum and Energy has provided a detailed response to a  parliamentary report that exposed financial gaps and structural delays in the country’s flagship energy projects.

Nani Juwara on Monday responded to the findings of the Public Enterprise Committee (PEC), on the reports of the projects implemented by NAWEC, namely GERMP,  GEAP, and ECOREAP.

Addressing the findings on Gambia Electricity Restoration and Modernization Project (GERMP), where auditors flagged GMD 1.72 billion in direct financier-to-contractor payments that completely lacked recipient signatures or receipts, Juwara asserted that the matter “has now been fully resolved” with robust controls to ensure compliance.

The Public Enterprise Committee indicated that payments to contractors were processed directly through the financier.

However, PEC noted that payment acknowledgements from beneficiaries were not consistently obtained.

“Audit review identified payments amounting to GMD 1,720,588,939.33 without receipts and recipient signatures, limiting audit assurance and weakening financial accountability,” PEC revealed.

In his responses, Minister Juwara said “Management has duly noted this observation and wishes to inform this August Assembly that the matter has now been  fully resolved, with robust measures instituted to prevent recurrence in subsequent audits”.

Regarding the withholding tax non-compliance, PEC disclosed that “the audit identified failure to 

withhold tax amounting to GMD 258,364,338.07″, which the management indicated has been corrected in subsequent transactions. 

The Committee considers this a serious compliance weakness requiring stronger tax controls.

In his response, Miniater Juwara said that the initial operational understanding was that project funds enjoyed tax exemptions, which accounted for the omission of withholding taxes on contract payments. 

He explained that following the Ministry of Finance and Economic Affairs (MoFEA) directive issued in 2024 regarding mandatory withholding tax on contracts, the project management office promptly notified all contractors, consultants, and suppliers. 

However, he argued that the directive should apply exclusively to new contracts executed post-directive. 

He added: “Existing contracts are legally binding, were negotiated without provision for this tax, and its retroactive enforcement could severely impair contractors’ execution capabilities.”

“This stance has been formally communicated to the Ministry of Finance and Economic Affairs,” he said.

Regarding land acquisition and compensation delays, PEC stated that Project execution was affected by land acquisition and compensation challenges, including disputes with landowners and delays in meeting compensation thresholds.

Miniater Juwara said: “While not explicitly highlighted in the 2023 audit findings, the delays experienced in this component of the project stemmed primarily from limitations within the Resettlement Action Plan (RAP) study, which was conducted during the COVID-19 pandemic”.

Consequently, he said these constraints hindered comprehensive outreach and the accurate mapping of all Project Affected Persons (PAPs) alongside their corresponding compensation valuations.

On GEAP, he acknowledged the significant implementation delays reported by PEC and has instituted remedial measures with the contractor. 

According to PEC, Management attributed the delay partly to the allocation of a large number of communities to one contractor, thereby overstretching contractor capacity.

He replied: “The contractor was directed to submit a revised mitigation plan to serve as a benchmark for evaluating progress against the extended timeline, supported by rigorous monitoring schedules enforced by the PIU and the Owner’s Engineer (OE).”

Regarding ineffective contract structuring, the Committee observed that project packaging did not adequately consider the scale and geographical spread of works.

PEC said: “Large single contracts limited competition, supervision and timely delivery.”

He replied that Project management Office acknowledges this observation but clarifies that contract packaging was executed at regional level by the ECOWAS Regional Coordination Unit as part of the overarching implementation framework involving participating member states such as Guinea-Bissau and Mali.

Speaking on the fuel allocation on ECOWAS Regional Electricity Access Project  (ECOREAP), Juwara clarified that the projector allocated fuel to vehicles which were used under the project l.

“All non-ECOREAP vehicles that drew fuel during the review period were deployed exclusively for official ECOREAP assignments, including technical site visits and environmental and social safeguard monitoring missions,” he said.