The National Water and Electricity Company (NAWEC) has attributed the recent electricity outages affecting the Greater Banjul Area to technical challenges and ongoing maintenance works, dismissing speculation that the disruptions are linked to financial disputes or strained bilateral relations with electricity suppliers in Senegal and Guinea.

Speaking at a press conference held at the Sir Dawda Kairaba Jawara International Conference Centre and hosted by the Ministry of Information and Broadcasting Services, NAWEC Deputy Managing Director Sompou Ceesay said the utility company remains committed to restoring stable electricity supply despite the current challenges.

Mr. Ceesay explained that the outages experienced over the past two weeks were caused by technical glitches beyond the company’s control and not by any failure to meet its financial obligations to regional energy suppliers. According to him, NAWEC maintains bank guarantees with its suppliers, including Senegal’s SENELEC, which serve as financial security mechanisms in the event of any contractual breaches.

He revealed that several of NAWEC’s generators are currently undergoing extensive repairs and maintenance as part of efforts to strengthen domestic power generation.

The utility has spent more than US$1 million from its own resources on generator rehabilitation over the past 12 months and expects to spend an additional US$2 million on maintenance and repairs within the next year.

Mr. Ceesay further disclosed that NAWEC has spent over US$1 million since January on fuel purchases aimed at enhancing the country’s energy security amid increasing operational costs. He also highlighted the impact of global developments, particularly the conflict involving Iran, on the regional energy sector. According to him, rising oil prices have placed pressure on thermal power plants across the region, reducing available surplus electricity and affecting energy imports.

He added that the conflict has also contributed to delays in the delivery of spare parts and the extension of maintenance schedules.

Providing an update on regional electricity imports, Mr. Ceesay explained that The Gambia remains connected to the Organisation pour la Mise en Valeur du Fleuve Gambie (OMVG) regional electricity network, which links four member states through approximately 1,500 kilometres of 225kV transmission lines. He noted that the country’s electricity system is highly integrated with those of Senegal and Guinea.

Looking ahead, Mr. Ceesay announced plans to improve electricity generation through a new 50-megawatt solar power plant in Soma and a rapid recovery programme aimed at restoring approximately 50 megawatts of generation capacity. He said more than US$3 million has already been invested in maintenance works over the past year.

Beyond electricity, he highlighted several water sector projects being implemented by the utility, including the procurement of more than 50,000 water meters, the construction of seven new water tanks with capacities of 1,000 cubic metres each, and a new water treatment plant in Tujereng—the first such facility to be built since 2009.

While apologising for the inconvenience caused by the recent outages, Mr. Ceesay said it is not in NAWEC’s interest to deliberately deny customers electricity, noting that the disruptions have also resulted in financial losses for businesses and individuals. However, he did not provide any assurance regarding compensation for affected consumers.