President Adama Barrow has stressed the need for the timely completion of the BB Hotel Bridge in Kotu ahead of the upcoming tourism season.

President Barrow made the remarks on Tuesday during an inspection tour of the ongoing reconstruction works at the BB Hotel Bridge, commonly known as the Kotu Bridge, as part of a visit to two major infrastructure projects.

Accompanied by the Minister of Transport, Works and Infrastructure, Ebrima Sillah, and officials of the National Roads Authority (NRA), the President inspected the progress of works at the bridge, which is located within the Tourism Development Area.

Officials said the bridge is expected to be completed by October 27, 2026, although some additional road construction works could continue into the second week of November.

The project coordinator said efforts are being made to increase the workforce while maintaining quality standards as the deadline approaches. He also said heavy rainfall had contributed to delays in the project.

President Barrow stressed the importance of completing the bridge ahead of the upcoming tourism season, given the area’s significance to the country’s tourism industry.

The BB Hotel Bridge has been in a state of disrepair, affecting movement and business activities around Kotu, Fajara, hotels and markets.

From Kotu, President Barrow proceeded to the Sukuta-Jabang Traffic Light Flyover, where he also inspected ongoing construction works.

The flyover, being implemented under Phase Three of the Bertil Harding Highway Project, is about 90 percent complete, with all major structural works completed.

The contractor, Arezki S.A., is expected to commence waterproofing of the bridge deck before asphalt surfacing of the deck slab and roundabout.

Installation of handrails is also ongoing and is expected to be completed by Friday, September 25.

Other remaining works, including street lighting, road signage and painting, are scheduled for completion by the end of November 2026.

Speaking to the press after the inspection, President Barrow said the Sukuta-Jabang Flyover would be opened to traffic by the end of October.

He said the approximately US$7.8 million flyover was introduced to address congestion at the Sukuta-Jabang roundabout and improve traffic flow for commuters.